Copper price indexing in supply agreements

Most copper parts are quoted on a reference price that moves. The clause that decides how it moves matters more than any single quote.

QKQumek Trade Desk··9 min read·Updated
INFOB

Key takeaways

  • A copper index clause links the material portion of the price to a published reference, not to the supplier's buying price.
  • The clause needs a reference, an averaging period, a premium, a conversion charge and a yield assumption.
  • Bands limit small adjustments, while caps and collars decide who carries larger moves.
  • Scrap recovery and yield change the real material cost, so the clause should state how they are treated.

What an index does and does not do

A copper index clause separates the metal value from the rest of the part price. The metal value follows a published reference, usually the London Metal Exchange cash settlement or a monthly average. The conversion, the finish and the margin stay in the supplier's control.

The index is not the supplier's purchase price. A fabricator buys metal with a premium over the exchange, and the premium depends on the product form, the quantity, the delivery point and the credit terms. The index is a common starting point, not a full description of the cost.

The clause also does not decide the whole commercial relationship. It sits inside a price that includes labour, tooling, energy, packaging and freight. Indexing only the metal line leaves the rest of the price to normal negotiation and review.

A good clause is readable by both sides without a spreadsheet argument. It names the source, the date and the unit, and it produces the same number whoever calculates it. If the parties need a meeting to agree what the index means, the clause is not finished.

The three parts of a copper price

The first part is the exchange reference. It is the published price for a defined grade and contract, expressed in a currency and a unit. The reference should name the market, the grade, the currency and the unit, because a tonne price and a pound price are not interchangeable.

The second part is the premium. It covers the cost of turning the exchange product into the form the supplier buys: rod, strip, bar or profile. The premium also reflects freight to the supplier and the commercial terms. It is usually quoted separately and held for a period.

The third part is the conversion. That is the supplier's charge for melting, casting, rolling, drawing, machining, annealing or finishing. It is not a metal cost, and it should not move with the index unless the contract says so.

A clause that says price follows copper without separating these parts leaves the supplier free to apply the index to the whole price. That is not an index clause. It is a price increase with a reference attached.

Choose the reference and the averaging period

Copper is traded in several currencies and several contract months. A clause should state the exact reference: which exchange, which grade, which quotation and which currency. If the price is in another currency, state the exchange rate source as well.

The averaging period matters as much as the reference. A monthly average smooths daily spikes. A single day's quote can be gamed by timing the order, or can land on an unusual day. A quarter average is slower to react and reduces administration.

The timing of the reset should match the production cycle. If the supplier buys metal a month before shipment, a reset on the shipment date leaves a gap. If the buyer sets the price at order date, the supplier carries the metal risk between order and purchase. Either can work if it is written down.

Holidays and market closures also matter. A monthly average that relies on a single fixing can be distorted if the fixing date falls on a day with no publication. The clause should say what happens when the reference is not published, such as using the next available day or the previous published value.

Name the quotation, not just the metal

LME copper is a family of prices. The clause should identify the contract, the settlement basis, the currency and the unit.

The pass through formula

A practical formula prices the finished part as the metal content plus the conversion and other agreed charges. The metal content is the input mass required per finished part, multiplied by the reference price plus the premium. The input mass includes the yield loss.

The worked example below is illustrative. It uses a round reference price and a simple yield so the arithmetic is visible. The numbers are not a market forecast or a supplier quotation.

Illustrative copper index build for one finished kilogram
LineBasisAmount
Exchange reference9,000 USD per tonne, illustrative9.00 USD per kg
Premium250 USD per tonne, illustrative0.25 USD per kg
Metal per kg of inputReference plus premium9.25 USD per kg
Input mass per finished kg1.15 kg, allowing for yield10.64 USD
Conversion chargeFixed for the period1.20 USD
Indexed price per finished kgMetal content plus conversion11.84 USD

Illustrative only. The reference, premium, yield and conversion depend on the part, the mill product and the agreement. Confirm market data with the supplier and the exchange.

Bands, caps and dead zones

A band ignores movements inside a stated range. If copper moves less than the band, the price stays the same. That removes small adjustments and the administration that comes with them. The supplier absorbs the movement in one direction and the buyer in the other, depending on how the band is written.

A cap limits the buyer's exposure above a level. The supplier may price the cap into the base price, because it is carrying risk. A floor does the same for the supplier. Neither is free, and neither should be added without checking the base price.

A collar combines a floor and a cap. It is useful when both sides want a predictable range. The risk is that a large move outside the range is deferred rather than resolved, so the contract needs a review trigger for a sustained breach.

The band should be expressed on the same basis as the index, not on the finished price. A five percent band on the metal content is a different amount from a five percent band on the whole part. State the base and the arithmetic, or the clause will be read two ways.

Scrap, yield and the real material cost

Not every kilogram of copper bought becomes a finished part. Cutting, stamping, machining and set up produce scrap. Some scrap is recovered and sold, some is lost in the process, and some is tied up in work in progress.

If the clause uses the finished weight and ignores yield, the supplier absorbs the difference. If it uses the input weight and ignores scrap recovery, the buyer pays for metal that is sold back. The fair method states the yield assumption and the scrap credit separately.

Scrap value is not the same as the exchange price. It carries a discount that depends on the form, the cleanliness and the buyer. A clause that credits scrap at the full index overstates the recovery. Agree the discount or the credit basis explicitly.

The yield assumption should be tested at the start of a programme and when the process changes. A new tool, a different strip width or a change in the nesting can move the input mass. If the clause is not updated, the buyer and the supplier can both be right on their own numbers and still disagree on the invoice.

Governance and evidence

An index clause is only as good as its records. Each reset should be supported by the published reference, the averaging calculation, the exchange rate if one is used, the premium in force and the yield assumption. Without those, the invoice cannot be checked.

Set a review cadence and a dispute route. If the published reference is unavailable, the clause should name a fallback. If the parties disagree about the premium, the agreement should say how it is reviewed. If a part changes weight or material grade, the formula inputs need to be updated before the next order.

Record the version of the clause that applied to each shipment. A clause that is amended without a version number makes a retrospective audit difficult, because the invoice cannot be tied to the wording in force at the time.

  1. 01

    Name the reference

    Exchange, grade, quotation, currency and unit.

  2. 02

    Set the average

    Daily, monthly or quarterly, with the reset date.

  3. 03

    Separate the premium

    State the form premium and its review period.

  4. 04

    Fix the conversion

    Keep the processing charge out of the metal index.

  5. 05

    State the yield

    Input mass, scrap credit and the recovery basis.

  6. 06

    Record each reset

    Keep the published data and the calculation with the invoice.

Frequently asked questions

What is a copper price index clause?

It is a contract mechanism that links the metal portion of a part price to a published copper reference. The clause should state the reference, the averaging period, the premium, the conversion charge and the yield assumption.

Should the whole part price follow copper?

No. Only the metal content should follow the index. Conversion, finish, tooling and margin are separate costs. Applying the index to the whole price turns a metal pass through into a general price increase.

What is a dead band in a metal clause?

A dead band is a range inside which the price does not change. It removes small adjustments from the process. The contract should state who carries movements inside the band and what happens outside it.

How is scrap treated in an indexed price?

The clause should state the yield assumption and the scrap credit separately. Scrap is usually valued below the exchange price, so crediting it at the full index overstates the recovery.

Sources and further reading

  • London Metal Exchange, copper contract specifications and reference prices
  • International Chamber of Commerce, Incoterms 2020
  • Qumek trade desk, metal index and should-cost notes
QK

Qumek Trade Desk

Trade and logistics team

The team that handles Incoterms, customs classification, freight and landed cost for Qumek programmes.

Building a metal index clause?

Send the part, the material form and the current quotation. The trade desk will set out the reference, the yield assumption and the reset method to agree.

Ask the trade desk
Sourcing9 min read

Currency exposure and quotation validity

A price is only valid on the assumptions behind it. Currency, metal and freight can move before the purchase order is placed, and the contract decides who absorbs the difference.

Read
Sourcing9 min read

Should-cost modelling for custom parts

A should-cost model builds the price from the process before the quote arrives. It gives a buyer a defensible range and a list of questions, not a single number to argue about.