Key takeaways
- A should-cost model starts with the process route and the material input, not with the supplier's price.
- Build the cost in blocks: material, conversion, tooling, finish, packing, freight and margin.
- Use the model to find the gap and the reason for it. A model that is treated as the true price becomes a negotiation trap.
- Update the inputs when the design, volume or route changes, and record the assumptions with a date.
What a should-cost model is
A should-cost model is an independent estimate of what a part ought to cost, built from the process, the material and the volume. It is not a supplier's quote and it is not a market price. It is a structured view of the cost drivers that both sides can inspect.
The model is useful because a quote is a single number with the workings hidden. If the number looks high, the buyer cannot tell whether the material assumption, the cycle time, the tooling amortisation or the margin is responsible. A should-cost model separates those lines and shows where the difference sits.
It is not a substitute for a quote. The supplier knows its equipment, yield and overhead better than the buyer does. The model is a challenge tool: it produces questions, and the answers either explain the gap or reveal an error.
A model is also useful before a drawing is finished. If the concept needs a tight tolerance, a second operation or a specialised material, the model shows the cost effect while the design can still change. That is the point at which the model has the most value, because the cheapest fix is a design change, not a negotiation.
Start with the process route
Before any arithmetic, write the route. A stamped part might run blank, pierce, form, trim and finish. A machined part might run saw, turn, mill, deburr and plate. A wireform might run straighten, feed, bend, cut and finish. Each step has a machine, a cycle time and a labour content.
The route decides the cost blocks. A part with a plating step carries a finish cost and an inspection cost. A part with a welded joint carries a fixture and a test. A part with a tight tolerance may need a second operation or a slower cycle. The route is where the model earns its credibility.
State the assumptions that are not visible on the drawing: the material form, the stock size, the number of parts per stroke or per bar, the scrap rate, the setup time and the batch size. A model without those is a guess with a spreadsheet around it.
The route should also include the inspection and packing steps. A part that needs a first article, a load test or a dimensional check at every batch carries a cost that does not appear in the machine cycle. Packing can be a small line, but it becomes significant when the part needs protection, separation or a clean room.
The building blocks
Material is the input mass multiplied by the material price, less any scrap credit. The input mass is not the finished weight. It includes the runner, the blank, the cut off or the machining allowance. The material price should match the grade, the form and the quantity the supplier would buy.
Conversion is the machine time and the labour to run the route. It usually includes setup spread across the batch, the cycle time per part and the burden rate for the equipment. The burden rate is the hardest input to verify, because it includes depreciation, space, power and indirect labour.
Tooling is either a one off charge or an amortised cost per part. Finish, packing and freight are separate lines, because they are often quoted separately and can be compared. Margin is a percentage or a fixed add, and it should be visible rather than folded into conversion.
The sum of the blocks gives a should-cost range. A range is more honest than a point estimate, because several inputs are uncertain. Present the low, mid and high case, and say which assumption drives the spread.
A worked example
The table is an illustrative build for a stamped copper part at an annual volume of 10,000 pieces. The numbers are round and the process is simplified. They show the structure, not a market price.
| Block | Basis | Cost |
|---|---|---|
| Material | 0.42 kg input at 14.76 per kg | 6.20 |
| Conversion | Cycle time, setup and burden rate | 2.40 |
| Finish | Plating and handling | 0.95 |
| Tooling | 7,000 amortised over 10,000 pieces | 0.70 |
| Packing | Carton, divider and label | 0.35 |
| Freight | Share of the inbound or outbound leg | 0.45 |
| Overhead and margin | Applied to the conversion and material base | 1.80 |
| Should-cost per part | Sum of the blocks | 12.85 |
Illustrative only. Material price, cycle time, burden rate, tooling and margin depend on the part, the supplier and the volume. Confirm the inputs before using the model.
Where models go wrong
The most common error is using the finished weight as the material input. That understates the cost whenever the process produces scrap. The second is using a material price from a small quantity catalogue when the supplier would buy a coil or a mill lot. The third is ignoring the setup cost at low volume.
Another error is applying a generic burden rate to a specialised machine. A five axis machining centre and a mechanical press do not carry the same hourly cost. A model that uses one rate for every process will be wrong on at least one of them, and often in a way that flatters the wrong supplier.
The model can also be too precise. A should-cost built to four decimal places from estimated cycle times implies a confidence that does not exist. Round the output to a sensible range and show the sensitivity. Precision is not the same as accuracy.
A final error is to ignore the cost of quality. A supplier with a lower conversion rate may carry a higher reject rate, more sorting and a higher safety stock. The should-cost should include the expected yield and the inspection burden, or the comparison will favour the supplier that looks cheapest before the rejects are counted.
The gap is the deliverable
A should-cost that differs from the quote is useful only if it explains why. Identify the block and the assumption behind the difference.
Using the model in negotiation
Do not open with the number. Open with the route and the assumptions. Ask the supplier whether the material form, the cycle time, the scrap rate and the tooling amortisation are right. A supplier that engages with the inputs is easier to work with than one that defends a total.
If the gap is in material, ask for the mill certificate, the input weight and the scrap credit. If it is in conversion, ask for the cycle time, the number of cavities or stations and the setup. If it is in tooling, ask for the tool cost breakdown. Each question has an evidence trail.
The model also helps with a volume change. If the annual quantity doubles, the setup and tooling per part fall, but the material and conversion do not fall by the same proportion. A model shows the shape of the curve, so the buyer can test whether a volume break is credible.
Maintaining the model
Date every input. Material prices, exchange rates, labour rates and freight move. A model built on last year's assumptions can be worse than no model, because it looks authoritative while being stale.
Keep the source for each input: the quote, the index, the drawing, the time study or the supplier's breakdown. When the design changes, update the route and the input mass before the next quote. When the volume changes, update the setup and tooling amortisation.
Review the model with the supplier at the start of a programme, not only when a price is disputed. That turns it into a shared cost structure and reduces the chance that a future increase arrives without a shared basis for discussion.
Keep a short note of what changed between versions. A model that is updated without a history cannot explain why the estimate moved, and the buyer may end up defending a number that no longer reflects the process. Version control is part of the model, not an extra.
- 01
Fix the route
List every operation, machine and inspection step.
- 02
Set the inputs
Material form, input mass, cycle time, scrap and batch.
- 03
Build the blocks
Material, conversion, tooling, finish, packing, freight, margin.
- 04
Test the range
Run low, mid and high cases and identify the driver.
- 05
Compare
Put the model beside the quote and explain the gap.
- 06
Record and review
Date the inputs and update when the design or volume changes.
Frequently asked questions
What is the difference between should-cost and a quote?
A quote is the supplier's offer. A should-cost is the buyer's independent estimate built from the process and material. The model is used to test the quote and to ask better questions, not to replace the supplier's price.
How accurate should a should-cost model be?
It should be accurate enough to show the range and the main cost driver, not to the last decimal. Several inputs are estimates, so present a low, mid and high case and state which assumption drives the spread.
What inputs are needed for a should-cost model?
The process route, material grade and form, input mass, scrap rate, cycle time, batch size, tooling cost, finish, packing and freight. The supplier's quote and breakdown are useful for comparison, but the model should stand on its own inputs.
Should the model include the supplier's margin?
Yes, as a visible line. A model that excludes margin produces an unrealistically low number. Use a range that reflects the work, the risk and the volume, and discuss the margin separately from the cost blocks.
Sources and further reading
- International Chamber of Commerce, Incoterms 2020
- London Metal Exchange, reference prices and contract specifications
- Qumek trade desk, should-cost and cost breakdown notes
Qumek Trade Desk
Trade and logistics team
The team that handles Incoterms, customs classification, freight and landed cost for Qumek programmes.
Want a second view of a quote?
Send the drawing, the volume and the supplier's breakdown. The trade desk will build the cost blocks and show which assumption explains the gap.
Ask the trade desk