Key takeaways
- APQP is a five phase method for developing a product and the process that will make it.
- Each phase ends with a gate decision and a defined output, not a meeting.
- The process flow, PFMEA and control plan are built in phase three, before validation.
- Most launch failures come from starting process design before the product design is fixed.
What APQP is
Advanced product quality planning is a structured method for developing a product and the process that will make it. It starts with the customer's needs and ends with a launched part, a stable process and a record of what should change next time.
The method has five phases and a set of gate reviews. The phases are not a waterfall. Design and process work overlap, and a supplier may be buying tooling while the drawing is still moving. The discipline is in the outputs: each phase has to produce something the next phase can use.
Phase 1: plan and define the programme
The first phase turns a request into a programme. The team collects the customer's needs, the business case, benchmark data, reliability targets and any regulatory requirement. It builds a preliminary bill of material, a preliminary process flow and a product assurance plan.
The output is a set of design and quality goals with an owner and a date. The gate question is simple: is the programme defined, resourced and worth doing? A team that cannot answer that question will spend the rest of the project solving it in the tooling budget.
Phase 2: product design and development
The second phase makes the design real. The team completes the design FMEA, checks design for manufacturability and assembly, plans the design verification, builds prototypes and releases the drawings, specifications and material calls.
The output is a design that has been tested against its own verification plan. The gate question is whether the design meets the requirements, not whether the drawing looks finished. A drawing released before the verification results are reviewed is a schedule decision, not an engineering one.
The prototype is a learning tool, not the production part. Build it with the intended material and process where possible, measure it against the verification plan and record every deviation. A prototype made by hand can still prove a concept, but it cannot prove a production process.
Phase 3: process design and development
The third phase designs the manufacturing system. The team writes the process flow, the process FMEA and the control plan, then specifies the tooling, the gauges, the work instructions, the packaging and the operator training.
This is where the quality of the launch is decided. The flow diagram sets the steps. The PFMEA sets the risks and the actions. The control plan sets the controls, the sample size and the reaction plan. If those three documents are written by three people who never meet, the production line will show it.
The gate question is whether the process is ready to validate. That means the tooling is in place, the gauges are studied, the operators are trained and the control plan describes the process that will actually run.
Phase 4: product and process validation
The fourth phase runs the process and proves it. The team completes a significant production run, studies the measurement systems, calculates initial process capability, runs the production validation tests and evaluates the packaging.
The output is a production control plan and a submission pack, usually a PPAP. The gate question is whether the process makes conforming parts at the quoted rate, with the production tool, the production operators and the production material. A run that needed an engineer at every station has not answered that question.
Run at rate is the practical test. The line should make the quoted volume, with the quoted labour and the quoted cycle time, while the control plan is followed. If the run needs extra inspection or a slower cycle, the process is not validated yet, even when the parts are good.
Phase 5: feedback and corrective action
The fifth phase starts at launch and does not really end. The team watches variation, delivery and service performance, reduces the largest losses and records the lessons that should change the next programme.
The gate question is what the organisation will do differently. A lessons learned document that nobody reads is not an output. A change to the design guide, the PFMEA library or the supplier selection criteria is.
The gates and the timing
APQP is often drawn as five boxes in a row. In practice, phases overlap and the gate reviews are where the overlap is controlled. Each gate should have a named reviewer, a date and a decision: proceed, proceed with actions, or stop.
The table gives the main output and the exit question for each phase. Use it as a checklist, not as a substitute for the customer's own programme requirements.
Keep the gate record short. The date, the attendees, the documents reviewed, the open actions and the decision are enough. The value is in the decision and the follow up, not in the length of the minutes.
| Phase | Main output | Exit question |
|---|---|---|
| 1 Plan | Design goals and preliminary process flow | Is the programme defined and resourced? |
| 2 Product design | Drawings, specifications and DFMEA | Does the design meet the verification plan? |
| 3 Process design | Flow, PFMEA, control plan and tooling | Is the process ready to validate? |
| 4 Validation | Production run, capability and PPAP | Does the process make conforming parts at rate? |
| 5 Feedback | Lessons learned and improvements | What changes for the next programme? |
Where APQP goes wrong
The most common failure is starting phase three before the design is fixed. Tooling is ordered against a drawing that later changes, and the process validation is repeated on a new tool. The schedule loses more time than the design review would have taken.
The second failure is copying documents. A PFMEA from a similar part is a useful starting point, but it is not an analysis of this part. A control plan written for the auditor, rather than for the operator, will not control anything on the line.
The third failure is treating the gate as a meeting. A gate without a decision, an action list and a named owner is a status update. The programme moves on with open risks and finds them again at launch.
A gate is a decision, not a meeting
Record who attended, what was reviewed, what was open and who accepted the risk. That record is what makes the next gate meaningful.
Frequently asked questions
Is APQP only for automotive suppliers?
It began in the automotive supply chain and is still most formal there. Other industries use the same five phase logic because the sequence of defining the product, designing the process, validating and improving is general. The customer specific forms may differ.
How long does APQP take?
It depends on the part and the tooling. A simple part may run through the phases in a few months. A new moulded housing with a new tool and a new assembly can take a year or more. The programme timing plan should be built from the tooling and validation lead times, not from a target launch date.
What is the difference between APQP and PPAP?
APQP is the planning method that runs from concept to launch. PPAP is the evidence pack submitted at the end of phase four to obtain production approval. PPAP is one output of APQP, not a separate method.
Who owns APQP in a supplier organisation?
A cross functional team owns it, usually led by a programme or quality engineer with authority to hold a gate. Design, manufacturing, quality, purchasing and service all contribute. A single department cannot close the actions that belong to another.
Sources and further reading
- AIAG APQP, Advanced Product Quality Planning reference manual
- AIAG PPAP, Production Part Approval Process, fourth edition
- IATF 16949, Quality management system requirements for automotive production
Qumek Quality Desk
Quality team
The quality team responsible for first article inspection, PPAP packs, supplier audits and the records shipped with production parts.